Thursday
10:00
Phoned Sapphire, Matthew (complaints) not in, left message for Darren (manager, fibreglass) to phone me. No reply.

[The pool is now totally covered by the scaffold, boards and a tarpaulin, except for the skimmer box - at least I can check the chemical levels through that, though it's not ideal.
During this week, the footings and pilings were dug and poured, the rear gutter replaced by a structural, load-bearing one and by Friday the entire ring beam was in place with load bearing legs along two sides.
]

I really wish they could show even half the competancy of the conservatory builders, we might actually have a finished pool by now if they had!